Structuring cost control documents with multiple breakdown structures

Working in the field of cost management, you will very likely encounter long lists of commitments, actuals, and other cost data that need to be reported on a frequent basis. To ease the job of structuring this data, breakdown structures prove to be the answer. They allow otherwise flat data to be viewed under many angles, serving the needs of the various stakeholders in the project, e.g. management, clients, and engineers.

Cost Breakdown Structure and Work Breakdown Structure

You are probably familiar with the Cost Breakdown Structure (CBS) or Work Breakdown Structure (WBS). It has become a common practice for a WBS to be a required project cost management tool on most contracts and the CBS is often used for cost accounting and reporting. Breakdown structures can also be used to generate all kinds of metrics and benchmarking and can become an essential business intelligence tool for a project.

Separating budget items

For example, a cost report can be structured by separating the critical and non-critical budget items. This simple distinction makes it possible to focus your attention on the activities that drive the project’s performance, instead of being clouded by the less important data. 

 

The figure below shows the S-curves describing the current approved budget (red), as it is planned to be spent, compared to the actual expenditures (blue). The actuals are extrapolated up to the end of the project, indicating a slight underrun of the budget.

Figure 1: Current revised budget vs actual cost, forecasted to the project finish date. The graph was obtained using the cost management software Cleopatra Enterprise.

This seems like a favourable situation, but mind you, this is the graph of the total project cost. The total actual cost at any time is the sum of possibly many individual costs that run over and under the budgeted values. Some of these actuals have a significantly larger impact on the project outcome than others. Therefore, it is wise to filter out the less critical parts and re-evaluate the case.

 

Figure 2: Current revised budget vs actual cost, forecasted to the project finish date. Only the critical project scope is plotted. The graph was obtained using the cost management software Cleopatra Enterprise.

Figure 2 filters out the less critical parts and shows only the critical project scope. As you can see, this figure provides a totally different view from the one above, one that even shows a predicted overrun of the budget! To conclude, breakdown structures help you structure your cost data and reveal your project’s real performance.


About Cleopatra Enterprise

Cleopatra Enterprise is the innovative and industry-leading Project Cost Management Software for industries such as oil & gas, chemical, mining, pharmaceutical, infrastructure, and construction industries. With a mission to help companies complete projects within time and budget, Cleopatra integrates cost estimating, scheduling, cost control, and project benchmarking.

For more than 20 years, Cleopatra Enterprise has been used by more than 500 industry-leading companies in 75 countries to control technical projects and turnarounds and improve project performance. If you'd like to talk to an expert about our software Cleopatra Enterprise, please request a demo now.

Related articles

Increase Project Performance with the correct Cost Control Philosophy

The correct Cost Control Philosophy: Work Breakdown Structures (WBS)

4 improvements that led Enbridge to better cost estimating and benchmarking using Cleopatra

5 greatest benefits of using a Project Controls Software

Download Case Study

KCI Case Study